The leach field installation process begins with securing a permit from the Town you live in. Then from there a test pit is preformed adjacent to the leach field. From the information gained from the test pit it can be determined if your leach field can be replaced in- kind or if a new septic system design is required.

Once that has been completed, then the septic tank is pumped, so you can stay in the house while the work is being done. The site is now prepared for the installation of a new septic system. The septic system is installed in about three days, and after that time it is ready for use. (Note if a new septic system design is required that procedure take about four to six weeks to get approval)